1Project overview
A project management application built around a critical path method (CPM) scheduling engine.
2Objective
Develop a project management application with a critical path scheduling engine that can stand alongside tools like MS Project and Primavera P6.
3My role
- Building the application in Python with a Streamlit interface and SQLite database.
- Developing the CPM engine: forward pass, backward pass, float, and critical path.
- Using a 40-hour Monday–Friday working calendar with holidays excluded.
- Testing scheduling calculations with pytest.
- Planned next: schedule crashing and optimization with OR-Tools.
4Engineering approach
Scheduling engine first
The CPM math is built and tested before the interface grows around it.
Working calendar
Baseline schedules use a 40-hour Monday–Friday week with holidays excluded.
Tested calculations
pytest checks the forward pass, backward pass, float, and critical path.
Next
Schedule crashing and optimization with OR-Tools.
5Analysis and visuals
Image to add: App screenshot
A screenshot of the schedule or Gantt view from your app.
6Results and impact
Combines project controls, scheduling mathematics, and software development in one tool. This project is in development.