Proposed design

QRM Lead-Time Reduction

A Quick Response Manufacturing (QRM) redesign of an injection molding operation, modeled before any rollout.

  • −44% lead time, 18 → 10 business days Target
  • 38→71% share of time spent on actual work Target

1Project overview

A Quick Response Manufacturing (QRM) redesign of an injection molding operation, modeled before any rollout.

2Objective

Redesign an injection molding operation to reduce lead time from 18 to 10 business days.

3My role

  • Led system design and current-state capacity analysis.
  • Mapped queue, setup, and inspection delays and touch time.
  • Designed the future-state shop floor layout.
  • Compared smaller batches, point-of-use staging, and a focused cell (QROC).
  • Used QRM capacity analysis and MPX to model options before rollout.

4Engineering approach

  1. Current state

    Mapped where lead time goes: queues, setups, inspection delays, and actual touch time.

  2. Options

    Compared smaller batches, point-of-use staging, and a focused QRM cell (QROC).

  3. Modeling

    Used QRM capacity analysis and MPX to test each option before any change on the floor.

  4. Future state

    Designed the future-state shop floor layout around the selected option.

5Analysis and visuals

Future-state MCT map: 9.09 days total, 70.83% touch time (modeled)

Image to add: Current-state vs. future-state layout

Side-by-side shop floor layouts showing the focused cell.

Image to add: MPX model output

Lead time and utilization for each option you compared.

6Results and impact

  • −44%lead time, 18 → 10 business days (target)
  • 38→71%share of time spent on actual work (target)

These are proposed future-state targets from the model, not completed operational results.

7Tools and technologies

  • Quick Response Manufacturing
  • MCT mapping
  • MPX
  • Capacity analysis
  • Layout design
  • Batch sizing